Section 11.09
Timing of Planting. All required plant material shall be planted prior to issuing a Final Certificate of Occupancy. In the event that the project is completed during a time of year when planting is impractical, a financial guarantee in the amount of the remaining improvements shall be provided in a form of payment acceptable to the Village.
Completion of Improvements. Tree stakes, guy wires and tree wrap shall be removed after completion of the initial growing season.
Irrigation. All landscaped areas in commercial or industrial districts shall be provided with an underground irrigation system.
4. Maintenance. Landscaped areas and plant materials required by this chapter shall be kept free from refuse and debris. Plant materials, including lawn, shall be maintained in a healthy growing condition, neat and orderly in appearance in accordance with the approved site plan. If any plant material dies or becomes diseased, it shall be replaced within thirty (30) days written notice from the Village or within an extended time period as specified in said notice.